Pass PMI PMI-RMP exam Dumps 100 Pass Guarantee With Latest Demo [Q55-Q73]

Share

Pass PMI PMI-RMP exam Dumps 100 Pass Guarantee With Latest Demo

The  PMI-RMP PDF Dumps Greatest for the PMI Exam Study Guide!


The PMI PMI-RMP exam covers a range of topics related to risk management, such as risk identification, assessment, response planning, and monitoring and control. PMI-RMP exam is designed to test the candidate’s knowledge and understanding of these topics, as well as their ability to apply them in real-life scenarios. PMI-RMP exam also assesses the candidate’s ability to communicate effectively with stakeholders and to work collaboratively with team members to manage risks.


PMI-RMP (PMI Risk Management Professional) Certification Exam is a certification offered by the Project Management Institute (PMI) to professionals who specialize in risk management. PMI Risk Management Professional certification is designed to evaluate a candidate's knowledge and expertise in identifying, assessing, and managing project risks. PMI-RMP certification holders are recognized for their ability to assess and mitigate risks, which is a valuable skill in project management.


In order to be eligible to take the PMI PMI-RMP certification exam, individuals must have a minimum of three years of experience in project risk management and have completed at least 30 hours of formal risk management education. PMI-RMP exam is computer-based and consists of 170 multiple-choice questions that must be answered within a four-hour time frame.

 

NEW QUESTION # 55
A company is executing a high-visibility project to develop mobile phone technology. The project sponsor is concerned that an overall high risk rating may undermine support for the project within the company. The sponsor has instructed the project manager to manipulate the data used for Monte Carlo simulation to artificially reduce the risk rating. What should the project manager do?

  • A. Modify the data.
  • B. Schedule a face-to-face meeting with the project sponsor.
  • C. Email the project sponsor explaining why the data should not be modified.
  • D. Ignore the request.

Answer: C

Explanation:
Explanation


NEW QUESTION # 56
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?

  • A. Costs
  • B. Human resource needs
  • C. Quality control concerns
  • D. Risks

Answer: D


NEW QUESTION # 57
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation.
How should the probability and impact be characterized for this risk?

  • A. Low probability/low impact
  • B. High probability/high impact
  • C. Low probability/high impact
  • D. High probability/low impact

Answer: B


NEW QUESTION # 58
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?

  • A. Add more contingency to the project
  • B. Review the plans for the key activity
  • C. Add more float to the key activity
  • D. Increase the budget for the key activity

Answer: B

Explanation:
The risk manager should recommend that the project manager review the plans for the key activity, as this will help identify potential issues and opportunities to improve the activity's performance and reduce its impact on the critical path.
The risk manager should recommend the project manager to review the plans for the key activity, which is now on the critical path according to the Monte Carlo simulation. The critical path is the sequence of activities that determines the minimum possible duration of the project. Any delay on the critical path will affect the project completion date. Therefore, it is important to review the plans for the key activity and identify any potential risks, issues, or opportunities that may affect its performance. The risk manager and the project manager should also evaluate the feasibility and effectiveness of any risk response strategies for the key activity, such as fast-tracking, crashing, or resource optimization. The other options are not appropriate recommendations for the risk manager to make. Adding more float to the key activity is not possible, since the critical path has zero float by definition. Adding more contingency to the project may not address the specific risks or issues related to the key activity. Increasing the budget for the key activity may not improve its duration or quality, and may also increase the project cost baseline unnecessarily. Reference: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications, page 91. A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Sixth Edition, pages 215-2162. Project Critical Path Analysis Using Monte Carlo Simulation3.


NEW QUESTION # 59
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?

  • A. Mark every identified risk as an extremely high priority and any future risks as a lower priority.
  • B. Ask the project sponsor if every risk in the risk register can have the same priority.
  • C. Agree with the SME, treat every risk with equal priority, and inform all stakeholders.
  • D. Perform a sensitivity analysis and determine the correct priority of every identified risk.

Answer: D

Explanation:
Explanation
The risk manager should perform a sensitivity analysis to assess the impact of each risk on the project objectives. This will help in determining the correct priority of every identified risk, ensuring that resources are allocated effectively and that the most critical risks are addressed first.


NEW QUESTION # 60
Rachel is the project manager of the KJH Project for her company. She needs a method to create a quick and simple approach to risk identification to communicate the project risk with the stakeholders. Which one of the following approaches to risk identification should Rachel choose to provide a quick and simple listing of the project risks?

  • A. Assumptions analysis
  • B. Delphi Technique
  • C. Checklist analysis
  • D. Brainstorming

Answer: C


NEW QUESTION # 61
After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.
What should the risk manager do to facilitate the sponsor's ask?

  • A. Quantitative risk analysis
  • B. Qualitative risk analysis
  • C. Sensitivity analysis
  • D. Monte Carlo analysis

Answer: C

Explanation:
Explanation
Quantitative risk analysis helps to numerically analyze the probability and impact of risks on project objectives. By performing quantitative risk analysis, the risk manager can present the risks with the most impact on achieving the project objectives to the project sponsor. (Reference: PMBOK Guide, 6th Edition, p.
423)
According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, sensitivity analysis is a type of probabilistic analysis that determines how sensitive the results of the analysis are to uncertainties in input variables. Sensitivity analysis determines which uncertainty has the greatest potential for an impact on the project objectives, such as cost, schedule, scope, or quality1. In this case, the risk manager should use sensitivity analysis to facilitate the sponsor's ask, as it will help to identify and present the risks that have the most impact on achieving the project objectives. Sensitivity analysis can also show how the project objectives will vary with the changes in the input variables, such as the probability and impact of risks2. Sensitivity analysis can be performed using various tools and techniques, such as tornado diagrams, spider charts, or influence diagrams3.
References: 1: PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, 2017, p. 403 2: PMI, Practice Standard for Project Risk Management, 2009, p. 95 3: Quantitative Risk Analysis in Project Management - PM-Training


NEW QUESTION # 62
During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.
What should the risk manager do?

  • A. Update the watchlist.
  • B. Initiate a risk response when these risks occur.
  • C. Perform a risk urgency assessment.
  • D. Address only the high-priority risk.

Answer: C

Explanation:
When a risk triggers several other risks that need a quick response, performing a risk urgency assessment is the appropriate course of action. This assessment helps determine how soon a response is required for each risk, considering their potential impact on the project. The PMI guidelines emphasize the importance of urgency in prioritizing risk responses, particularly when the consequences could significantly affect project deliverables if not addressed promptly.


NEW QUESTION # 63
Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?

  • A. Mitigation
  • B. Avoidance
  • C. Enhance
  • D. Transference

Answer: A


NEW QUESTION # 64
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?

  • A. Monitor and control secondary and residual risks in the risk register.
  • B. Identify secondary or residual risks for associated risk plans.
  • C. Update the communications management plan to avoid future issues
  • D. Develop risk response plans for all identified risks.

Answer: B

Explanation:
The project manager should monitor and control secondary and residual risks in the risk register. This will ensure that any new risks identified during the implementation of the risk response plan are captured and managed effectively. Monitoring and controlling risks is a continuous process that helps in identifying, analyzing, and planning for new risks as well as updating the risk register as needed.
According to the PMI Risk Management Professional (PMI-RMP)®Examination Content Outline, one of the tasks under the domain of Risk Response Planning is to "identify and assess the effectiveness of alternative strategies to reduce threats or enhance opportunities, such as mitigation, transference, avoidance, and acceptance" 1. This implies that the project manager should also consider the potential secondary or residual risks that may arise from implementing the chosen risk response strategy. Secondary risks are new risks that are created as a direct result of implementing a risk response, while residual risks are those that remain after the risk response has been executed 2. Both types of risks should be identified and assessed for their impact and probability, and added to the risk register for further monitoring and control. Therefore, the correct answer is A.
References: 1: PMI Risk Management Professional (PMI-RMP)®Examination Content Outline, page 91 2:
A Guide to the Project Management Body of Knowledge (PMBOKGuide) - Sixth Edition, page 4362


NEW QUESTION # 65
Who is responsible for the stakeholder expectations management in a high-profile, high-risk project?

  • A. Project manager
  • B. Project management office
  • C. Project risk assessment officer
  • D. Project sponsor

Answer: A

Explanation:
Explanation/Reference:


NEW QUESTION # 66
Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and she needs to express to her project team and to the management the importance of communication in this project.
She would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

  • A. 0
  • B. 1
  • C. 3,003
  • D. 6,084

Answer: C


NEW QUESTION # 67
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?

  • A. Delphi method
  • B. Checklist analysis
  • C. Focus group
  • D. Brainstorming

Answer: A

Explanation:
The risk manager should use the Delphi method in this situation, as this is a technique that can help resolve differences among experts and reach a consensus on the identified risks and their characteristics. The Delphi method is a tool used to make quick decisions with consensus. This technique consists of sending several sets of anonymous questions to each expert. This is followed by a group discussion after every round. The Delphi method can help the risk manager to solicit the opinions of all experts without revealing their identities. This way, the experts can express their views freely and honestly, without being influenced or intimidated by others. The Delphi method can also reduce personal bias, ego, or emotional conflict among the participants. The risk manager can use the results of the Delphi method to create a list of potential risks and their causes, effects, and probabilities. The other options are not appropriate techniques for the risk manager to use in this situation. Brainstorming is a technique that can help generate ideas and identify risks, but it may not be effective in resolving differences among experts, as it involves open and spontaneous discussion. Focus group is a technique that can help collect requirements and opinions from stakeholders, but it may not be suitable for resolving technical disagreements among experts, as it involves a moderated and structured discussion. Checklist analysis is a technique that can help identify risks based on historical information and lessons learned, but it may not be helpful in resolving differences among experts, as it involves a predefined list of potential risks. Reference: 3, 4, 5


NEW QUESTION # 68
You are the project manager of the GHG project for your company. You have identified the project risks, completed qualitative and quantitative analysis, and created risk responses. You also need to document how and when risk audits will be performed in the project. Where will you define the frequency of risk audits?

  • A. Schedule management plan
  • B. Risk response plan
  • C. Risk management plan
  • D. Quality management plan

Answer: C


NEW QUESTION # 69
You are the project manager of the NHH Project for your company and you have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Now, you would like to assign risk owners to the events. Which risk events should have risk response owners?

  • A. Only the risk events that are considered a negative risk event with a high risk rating
  • B. Each agreed-to and funded risk response should have a risk response owner
  • C. Each risk that has a risk response should have a risk response owner
  • D. Only the risks with a high risk rating

Answer: B

Explanation:
Explanation


NEW QUESTION # 70
A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.
What should the risk manager do first to understand the impact on project cost?

  • A. Prioritize after quantitative analysis.
  • B. Perform qualitative analysis.
  • C. Conduct a subject matter expert (SME) meeting.
  • D. Prioritize the stakeholders affected.

Answer: B


NEW QUESTION # 71
The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

  • A. Update the assumptions/exclusions register
  • B. Mitigate risks identified on the sensitivity analysis
  • C. Hire more resources and crash the schedule
  • D. Perform a qualitative risk analysis for the project

Answer: B

Explanation:
The project manager should mitigate risks identified on the sensitivity analysis to ensure the P90 date is met. Sensitivity analysis helps identify the most critical risks that have the potential to impact the project's completion date. By mitigating these risks, the project manager can increase the likelihood of meeting the P90 date.
According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, the P90 date is the date that has a 90% probability of being met or exceeded by the project completion1. The Monte Carlo analysis is a simulation technique that generates possible outcomes of the project schedule based on the probability distributions of the activity durations2. The sensitivity analysis is a technique that determines how different sources of uncertainty affect the project objectives, such as the completion date3. Therefore, the project manager should mitigate the risks identified on the sensitivity analysis, as they are the most likely to affect the P90 date. By reducing the uncertainty and variability of the project schedule, the project manager can increase the confidence level of meeting the P90 date.


NEW QUESTION # 72
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment What should the risk manager do?

  • A. Escalate the issue to the project board.
  • B. Review the feature with the project team.
  • C. Ask the architect to develop acceptance criteria.
  • D. Confirm the risk triggers are still valid.

Answer: B

Explanation:
Explanation
When a key feature may not be testable due to changes in the environment, the risk manager should review the feature with the project team to understand the issue, assess its impact, and determine the appropriate risk response. This collaborative approach ensures that the team has a clear understanding of the situation and can work together to address the risk.


NEW QUESTION # 73
......

Read Online PMI-RMP Test Practice Test Questions Exam Dumps: https://passguide.prep4pass.com/PMI-RMP_exam-braindumps.html